IEEE 2800 Working Group
Standard for Interconnection and Interoperability of Inverter-Based Resources Interconnecting with Associated Transmission Electric Power Systems

Timeline & Milestones

Timeline

*Project authorization request (PAR) approved by NesCom on May 21, 2021 (https://development.standards.ieee.org/myproject-web/app#viewpar/12623/9133); contact [email protected] and sign up for P2882 Working Group and Task/Project on IEEE SA myProject at https://development.standards.ieee.org/myproject-web/app#interests

 

Milestones

 

Deliverable Important Dates
Milestone: WG and Sponsor Approve WG Draft 5.1 January 2021
Mandatory Editorial Coordination (MEC) Draft 5.2 February 1 – March 8, 2021
Ballot Group Formation February 1 – March 8, 2021, balanced outcome with 466 subject matter experts
Comment Resolution Group (CRG) Formation February 8 – March 8, 2021, received 38 self-nominations
Stakeholder Webinars Webinars for national and international stakeholders

•Objective was to raise awareness for the open ballot group formation

•Reviewed i) purpose and scope of standard and ii) key draft requirements

•Provided step-by-step instructions for how to join the ballot group

February 2021: refer to https://sagroups.ieee.org/2800/resources/ for slide decks & recordings

Milestone: SA Initial Ballot of Draft 6.0 (successful) March 10 – April 10, 2021 with 79% response rate (>75% was required)

84% approval rate (>75% was required) | 1,407 comments received (659 are “must be satisfied”)

Comment Resolution Group meets weekly CRG resolved SA Initial Ballot comments
Public Review closed May 9, 2021 (search for “2800” at https://publicreview.standards.ieee.org)
CRG Comment Resolutions and Draft 6.1 Completed June 9, 2021
WG Approval of Recirculation Draft (Draft 6.1) June 9, 2021
Recirculation 1 (successful) June 10 – July 9, 2021, with 86% response rate (>75% is required)

89% approval rate (>75% is required) | 406 comments received (235 are “must be satisfied”)

Recirculation 1 – Comment Resolution July – August/September 2021*

July 21, 2021: CRG call, then SubGroup leads resolving SA Recirculation 1 comments, subsequent CRG calls TBD

CRG Comment Resolutions and Draft 6.2 Completed August/September 2021*
Recirculation 2 September 2021* (14 days + comment resolution)
Recirculation 3 November 2021* (5 days + comment resolution)
Milestone: Submission to RevCom Dec 11, 2021 or Feb / Mar / May 2022?*
Milestone: Publication Q1 or Q2 of 2022*

* Tentative dates